Project Delivery System: Negotiated General ContractOwner: Palmyra Eagle Area School DistrictLocation: Palmyra, WisconsinConstruction Duration: 17 monthsBuilding Square Footage: 165,000 sf. additions and remodel 18,400 sf. demolitionProject Description: The project began in the summer with work on the new football field, track and grandstand. Phase I started in the fall and included locker rooms, kitchen/cafeteria, five additional classrooms and a computer lab and a gymnasium. This phase was completed in approximately one year. Phase II commenced in the following summer and included a new library, classrooms, middle school tech and FACE, foreign languages additional computer labs, science rooms and offices. This phase was completed in approximately five months. |