Building Square Footage:
Additions - 165,000 Square Feet
Demoltions - 18,400 Square Feet
Construction Duration:
17 Months
|
Project Details:
The project commenced during the summer of 2003 with work on the new football field, track and grandstand. Phase 1 started in the fall of 2003 and included locker rooms, kitchen, cafeteria, music/band, woods/metals, classrooms, science, biology, chemistry, computer lab and a new gym. This phase was completed in August of 2004. Phase 2 commenced in the summer of 2004 and included a new library, classrooms, middle school tech and FACE, foreign language, additional computer labs, science rooms, and offices. This phase was completed in January of 2005. |